I want to move a project in No Phase to Cancelled phase, the project has to be moved to Prepartion before the Cancelled option is available.
Request clarification before answering.
Hi Venkat,
this is because the first phase in a phase configuration is a system required phase, hence the document needs to be moved through this phase.
/Anita