How to transfer vendor changes from SRM to ECC?

Former Member
0 Kudos
214

Hi guys, I have download ECC vendors from ECC to SRM Server. Now I create new vendor in SRM with transaction BP, What should by configured to transfer vendor from SRM to ECC.

Please suggest solutions if any for this.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Justin,

Unfortunately there is no standard way of transferring vendors from SRM to ECC. Do you have PI in your landscape?

Regards,

Nikhil

Former Member
0 Kudos

Thanks for your reply.

Yes, We have PI in our landscape.

Former Member
0 Kudos

Okay.

Then you need to ask your PI consultant to implement the scenario Supply_Base_Management. This will help you in transferring the suppliers from SRM to ECC.

Regards,

Nikhil

Former Member
0 Kudos

Thank you.

I will try this.

Former Member
0 Kudos

Hi, Nikhil , We have implment supply_base_management scnario in PI .

And business partner changes can be transfer to ECC. But there are erorr in receiving point, vendor information is not be synchroized, ONE new vendor is created in ECC.

I checked mapping in PI, ABABusinessPartner-PartnerID mapps to CREAMAS03-E1LFA1M-LIFNR directly. Is it right?

Former Member
0 Kudos

What do you mean by 'Not synchronizing'? Pl explain in detail.

The mapping you have mentioned is correct. So what is the issue now? Vendor has been transferred to ECC?

Nikhil

Former Member
0 Kudos

Thanks for your reply.

Change data in SRM on business partner was transfered to ECC, but ABABusinessPartner-PartnerID is not equal to LIFNR in backend system. So the synchronization is interrupted.