Hi...for vendor evaluation, sometimes a PO date change is acceptable and vendor should not be penalised so a statistical delivery date change is required. However if the PO has many line items, is there a way to update it for the entire PO without having to do it line by line?
Request clarification before answering.
Hi ,
Please try export the PO , mass change in excel and import.