on 2022 Jan 06 11:43 AM
Hi team,
We are currrently making cutover actions in order to move our test project in "Production" status.
Currently the project is in "in testing" status.
We are trying to follow steps but we are blocked in "testing" phase.
When adding a script test, no one are corresponding the document type we are implementing
See below:
Is there any step we forgot?
Thank you
Regards
Request clarification before answering.
Hi,
thank you it worked.
Good to know that the PO must be sent from test and not from production.
Also, always drop down until the bottom of the page to find the "go live" button which is a little bit small and at right side.
Regards
Lysa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lysa,
You can send a PO from your test system assuming that it is configured like that in your project->connection details.
In there you should have two connections configured one for TEST (which is your quality) and another one for PROD (which is PRD you are going live with).
Once you select skip test and get to the screen you attached in your previous post, you can send a PO from test system and this will be picked up by CIG. After that go-live button will appear.
Regards,
Prem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Lysa,
Instead of test script you can send message directly from SOAPUI/Postman.
For go-live button to appear you need to have one successful message.
Best Regards,
Manisha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.