on 2018 Sep 06 2:23 AM
Hello All,
I am looking out for a Solution to create PO from Contract in SAP SRM 7.0.
We have Extended Classic Scenario in place.(PS- We cannot switch back to Classic scenario ).
When we create PO from Contract, it removes Outline and Only Flat Service Line are seen in POs.
We contacted SAP for the same and SAP said this is how SAP SRM works for PO in extended Classic scenario. We are looking out for a solution where we can have Outline on PO line item if PO is created from Contract.
Note - If I create PO from RFx response then PO is created with Outline as Expected.I am removing GROUPING_LEVEL as blank.
Is there any parameter which we can set to enable Outline for Service POs.
We tried setting few parameters like ITM_TYPE as 'HIER' ; SUBTYPE as 'EP' , but its didn't help.
Any pointers to this problem is highly appreciated.
Thanks in Advance!!!
Regards,
Vikas
Request clarification before answering.
Hello Summer Wang
As PPS 2.0 is active in our landscape,we understand by tweaking the PS item types and Configurable item numbering, the hierarchy creation in SRM PO is possible and also the replication of the PO line items in a similar representation to the ECC
Could you please help by providing any pointers?
Thanks
Nag
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Customer,
Unfortunately, when manually create SRM PO (without PPS active ), it is not possible to create hierarchy.
However if PR had service outline hierarchy, transferred to SRM Shopping cart ,after assigning contract, and then converted to SRM PO.
This service outline hierarchy could be adopted in to SRM PO.
You could also add contract in PO item , if the draft PO was created from above PR directly I think.
Please understand directly add hierarchy in BBP_DOC_CHANGE_BADI maybe trigger error in transfer stage.
Best regards
Summer Wang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Customer,
Unfortunately in when manually create SRM PO (without PPS active ), it is not possible to create hierarchy.
However when PR as service outline hierarchy, transferred to SRM Shopping cart ,after assigning contract, and then convert to SRM PO.
This service outline hierarchy can be adopted in to SRM PO.
You could also add contract in PO item , if the draft PO was created from above PR directly I think.
Please understand directly add hierarchy in BBP_DOC_CHANGE_BADI maybe trigger error in in transfer stage.
Best regards
Summer Wang