Hi Experts,

I am working on SRM 4.0.

The scenario followed by us is extended classic scenario.

Is it possible to perform the cost distribution activity in change mode for the purchase orders which are already in approved status.

Please provide clarification on this scenario.

Regards,

Ashok

View Entire Topic
Former Member
0 Likes

Hi

Do you mean to change the cost distribution after PO created in SRM side?

Muthu

Former Member
0 Likes

Hi,

The change of PO is cost distribution is being done in SRM.

Here the PO value is very less and there is no approval involved for the PO.

So soon after assigning the vendor and completing the shopping cart, the purchase order is also being issued to the vedor.

For such POs in SRM we are not able to find the cost distribution icon in SRM.

This is a service call from our client.

Regards,