Hello Experts,

I need to reverse the confirmation done in February. But system had updated the status as “Error in Process”.

  1. I would like to know à

1)      How to overcome from this problem

2)      What is the root cause for this kind of issues? Sometime same error appears in shopping cart, sometime in PO

Could you please educate me on this.

Thanking you

Regards

SRK

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Likes

Hi Sharan,

Can you please check if you can find IDOC from Feb in SRM system for this GR. That should give you detail error why the Confirmation is failed to process in ECC system. Based on your question it looks like that GR is not proceed in ECC system and created Goods Receipt?

Please provide error details from IDOC to better understand your problem and provide solution.

Thank you

Ritesh

Former Member
0 Likes

Hi,

Can you please check note 906050?

Regards,

Nikhil

Former Member
0 Likes

Hi Nikhil,

Thanks for your response. But this note is talking about service receipt, but I have issue in indirect procurment,

Is there any ways too resolve this issue?

Thanking you

Regards

SRK

Former Member
0 Likes

Hi Sharan,

Also please let us know the error status of the confirmation from RZ20. This will clearly help us analyse why the confirmation is failing.

Regards,

Nikhil

Former Member
0 Likes

HI Nikhil and Ritesh,

Thanks for the reply. Yes there was issue in Idoc, There was an issue with asset closure in back end. After rectifying issue in ECC it went through.

Thanks for the support extended.