on 2011 Mar 09 9:38 AM
Hi All,
I would like to know the following details.
is CLM is part of E sourcing? is it merged with E-sourcing application or still available as Xapps CLM? What is the lates version?
Based on your experience what is the time period required for implementing the standalone CLM system. Could you please share best practices , project plan.
Thanks in advance
Siva
Request clarification before answering.
Hi Siva,
CLM is part of E-Sourcing only, but you can use only CLM functionality alone also.
Latest version: E-Sourcing 5.1 / CLM 2.0 Patch 08, Next version 7 will be released for customer probably in Jun/Jul 2011
Approximate time for implementation of stand alone CLM is around 6 months, rest depend on client requirements.
Regards
~Ankush Mittal