we send PO's to third party through Idoc's. we use program BUS2012_ICH_R3 routine SEND_PORDCR1 to create outbound Idoc's.

we are facing above an issue "Change indicators could not be uniquely determined in material mapping"(Message No. M_ 011), when BOM has more than one component for subcontract PO creation in S4HANA system. if BOM has one component , we are able to create outbound Idoc's.

Please give me hits to fix issue.

Thanks

Surya.K

dar_spenc21
Member
0 Kudos

Have you found a solution,? Facing same error

0 Kudos

Hi Surya,

check if you do not have duplicate key entries in the generated data (eg. the same item number for two different items etc.).