Hello Friends,

We are in SRM 5.0, Extended classic, SP level 15. Even though I had security give me SAP_ALL and real buyer's role to me, I still see the Change Confirmation button grayed out. I can create confirmation but not change.

Please advise. I am trying to simulate an issue -

SC create --> PO create --> Conf create --> reverse conf --> add line item to PO --> create confirm again.

I am not able to do the 4th step shown above since the button is grayed out.

Any ideas and suggestions appreciated.

Thank you all

Rao.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Likes

This was fixed by applying a note 1397705

Former Member
0 Likes

thanks . it waas included in sp16. thanks

Former Member
0 Likes

Hi Rao

run clean job and status job and do. you can do it.

- create confirmation

- return delivey

- create a confirmation which you did return delivery

button will be active.