on 2015 Nov 04 11:56 AM
We've recently upgraded to SRM 7 so I'm still learning all it's little tricks! At the shopping cart creation stage is there an option to choose not to issue the PO output the vendor?
This is a very basic question and ssomething I should really know, I'm ashamed to say I don't! I'm guessing the answer is no but I would really appreciate if someone would confirm this for me please.
I did workout that when editing a PO, if I go into 'Header'>'Output'>'Additional Output Requested Via' and I change the option from 'Email' to 'XML' the revised PO doesn't get issued to the vendor - I was just wondering if something like this can be applied at the shopping cart creation stage?
Many thanks,
Zena
Hi Zena,
As far as I know, there is no such functionalities in Shopping Cart to control whether or not to output its follow-on document (PO).
If you don't want to issue PO output at all at any stage, you may consider to set the action entry in the customizing table for PO (BUS2201) as inactive.
BBPC_ACTIONMAP
BUS2201 Output CL_BBP_ACTION_OUTPUT_PO
Regards,
Wendy