Can we change the fully approved SC?

Former Member
0 Kudos
166

Dear SAP experts,

We are in SRM 7.01 with backend ECC 6.05. I have a simple question, can we change a SC that is already fully approved? As in ECC, though the PR are already fully released, we can change the PR and as the result the PR release strategy can be restarted.

Can we have the same functionality for SC in SRM?

Best regards,

Josh

View Entire Topic
RobinJanke
Contributor
0 Kudos

Hi,

I think that in the sourcing cockpit you can change the shopping cart, however I don't think you can achieve editing while there are valid follow-on documents.

Regards,

Robin