on 2010 Nov 11 8:57 PM
Hello SRM Experts,
we are working on a SRM 6.0 classic scenario system. We move the PRs from R/3 4.6C backend to the SRM system via the report "BBP_EXTREQ_TRANSFER". No problem at all. The external requirement SC is created and afterward the PO is create through SoCo. If the PR requester changes the delivery date for one PR that have been lifted to SRM and there is an PO created the outbound queue in SMQ1 get stuck with the status ANORETRY and no message error shows up in SLG1.
Has anybody have this issue?
Thank you very much for your answers.
Kind regards
Célio Medeiros
Request clarification before answering.
Celio
Once a PR is pushed to SRM , you are not supposed to push it again for the changes to be updaed in SRM SC.
Make the changes in the SC and PR(in ECC) manually....if required
Regards
Virender Singh