on 2011 Jan 25 11:50 AM
Hi,
We have a limit SC with an assigned source of supply (contract). But after approval this SC becomes a PR in ECC and not a PO directly. We are in classic scenario and all SC with source of supply should do that (including limit orders).
What could be wrong?
br
Anders
Request clarification before answering.
Hello,
You can debug the cart transfer based on note 1173815.
Kind regards,
Ricardo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
when Buyer creates a limit shopping cart after approval PO must be created since partner function registered as 19 .
so kindly check any BADI implemented to change the above behavior .
Note 1243836 - Manual entry of invalid contract allowed in contract limit
Note 1417491 - Adding a contract is not allowed in limit Shopping Cart
Is it works fine without contract ?
sap rule
In the extended classic scenario, contract limit fields were enabled for limit Sopping Cart.
In the extended classic scenario, you cannot assign a contract to a limit item. In the classic scenario, you can, as long as the confirmation and invoice flag is checked (it is not possible if only the invoice flag is checked). However, this is possible in the local scenario,that is you can assign a contract to a limit item in the local case (not extended), if the invoice only flag is checked.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.