Hi everyone,
Is ther any standard way to assign a contrat for a requirement?
For example, in SRM I have a contratct for material A. We want when an external requirement or a shoping cart for this material is created, the system look for the contratc and automaticaly assign it.
I checked the option SAP Supplier Relationship Management>SRM Server>Sourcing>Define Sourcing for Product Categories with option Aut. Grouping, Sourcing for Items Without Assigned Source, but it doesn't works.
Thanks,
Iván
Request clarification before answering.
Hi,
You have to implement the BADI "BBP_SOS_BADI"
http://wiki.sdn.sap.com/wiki/display/SRM/Documentation+BBP_SOS_BADI
With Regards,
Malay