on 2020 Aug 07 3:52 PM
Dear Ariba community,
After having set up the Forecast committ process between IBP and Ariba and successfuly sent the Forecast to Ariba, we observe that the Forecast Commit quantities can be edited only in Daily buckets. This is despite maintaining Data Sharing Plans and Mappings in IBP at Monthly time period.
This seems contrary to what is seen in other implementations where the Forecast Commit can be edited and sent for different time levels thanks to the always appearing action buttons.
Our question is: how do we enable Forecast Commit quantites to be adjusted and sent at different time levels?
Best regards,
Martin Rejman
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hi Martin,
Were you able to accomplish your requirement? If yes, please feel free to share the solution here.
Best,
Ivan