cancel
Showing results for 
Search instead for 
Did you mean: 

Adding a new source system

Former Member
0 Kudos
162

Hi All

We have BW testing system BTO pointing to EJ0. Now client wants this to point to EJ5 which is their new testing system. So essentially BTO should point to EJ0 and EJ5 both.

I have figured out below activities

1. Create new connection from BTO to EJ5

2. No need of BDLS activity as this is a new source

3. Create a new transport path fro EJ5

4.Re import all data source related transformation from dev system so that it can also point to EJ5. Pl note in BTO it currently points to EJ0.

5. Re- init from EJ5 and further data loads.

Is it fine or i am missing anything?

Accepted Solutions (0)

Answers (1)

Answers (1)

S_Sriram
Active Contributor
0 Kudos