Lesson Learnt – Plan Driven Procurement Issue
•PDP Scenario SRM 5.0 Vs SRM 7.0
•PDP Issue
____________________________________________________________________________________________________________________________________
PDP SRM 5.0 Configuration Settings :-
Settings on SRM side:
Settings on ECC side:
Note- Communication between SRM and ECC is through RFC.

_____________________________________________________________________________________________________________________________________
PDP SRM 7.0 Configuration Settings:-
Note- From SRM7.0 , ECC6.0 (EHP4) ESOA is used so PI will be used for communication between ECC and SRM
Settings on ECC side:
_____________________________________________________________________________________________________________________________________
PDP Issue- Purchase Requisition is not getting Transferred from ECC to SRM
Landscape- SRM 7.01 and ECC 6.0 ( EHP5)
Solution:
Thanks,