cancel
Showing results for 
Search instead for 
Did you mean: 

How to extend Auto maintenance order generation

0 Kudos
188

Hello Team,

We are now using MRP for some spare parts which are assigned to GTL so that the requirements of spare parts can be run automatically.
But we have a problem that for some spare parts we have two months of planned delivery time. Now PM orders are generated only one month in advance.
So for these spare parts it might be late because material requirement would run out after PM order generation.

so how to extend the auto PM order generation from 1 month to 2 months.

Shrikant Hatwar

Accepted Solutions (0)

Answers (0)