2016 May 23 4:08 PM
Hi,
How to define 365 days in Year at Price Level, By default its taking 360 days in Year (In Time Base price )
But its taking 365 days default in Quantity base price. Please suggest .
Yatendra
2016 May 27 11:10 AM
Hi Yatendra,
Can you be little more specific about your scenario ?
Viz., what is the Time category you maintained ?
Thanks
Tatha
2016 May 28 11:12 AM
Hi Sir,
Fix charge slab is
0-300 KWH -> 225 / KW per month
300-1000 KWH -> 250 / KW per month
1000 to last KWH -> 275 / KW per month
So Please suggest how to make the price or any other standard way for get Fix charge on the basis of energy consumption ?
Regards,
Yatendra