Hi,
Can someone elaborate the meaning of the above two fields we see in Portions.
Currently we just have the below assumption.
Alloc. Date for billing:
- Any bill that is generated against a scheduled record using this portion, will be considered a bill for this date.
- Should be in Past (2 months without warning, over 2 months with warning)
Example:
- On the portion, If End billing period = 21.01.2000 & Allocation date = 21.12.1999
- If the scheduled record is for date 21.01.2001 (End billing period)
- The bill will be considered to be a bill for 21.12.2000
Scheduled Billing Date:
- Date from which any installation using this portion can be billed.
- If there is a gap of 30 days between End billing period and Scheduled billing date, the schedule records will reflect the same.
Example:
- On the portion, If End billing period = 21.01.2000 & Scheduled billing date = 25.01.2000
- If schedule record is for end billing period 21.01.2001
- Billing for 21.01.2001 cannot be done till 25.01.2001
Thanks,
Joshua.