2009 Feb 09 9:01 PM
IS-UT experts,
Does anybody know how to configure the meter reading center within TCODE E41G? Screen field TE422-ABL_Z
Any help would be appreciated. Please point me in the right direction!
Thanks,
Nick
2009 Feb 10 2:58 AM
Hi Nick Wells,
You can configure the meter reading center using the table TE426-Meter reading center
Please follow the below steps:
1.Using the T.code Se16 ,enter the table name TE426
2.In the same screen of se16,you click on the create icon on the left corner of the screen.
3.Then maintain u r entries and save it.
4.Now you can view the created entries of the meter reading center in the E41G .
Thanks
Sasi
2009 Feb 10 2:58 AM
Hi Nick Wells,
You can configure the meter reading center using the table TE426-Meter reading center
Please follow the below steps:
1.Using the T.code Se16 ,enter the table name TE426
2.In the same screen of se16,you click on the create icon on the left corner of the screen.
3.Then maintain u r entries and save it.
4.Now you can view the created entries of the meter reading center in the E41G .
Thanks
Sasi
2009 Feb 10 2:42 PM
Sasi,
thank you, we did the config via sm30. But your suggestion got us in the right direction.