Hello.

Can you describe what is the field in the table X_RED-IVB-EXTPKZ ? It is in FM of variants for example ISU_QUANTI01.

I understand that it something about extrapolation but what exactly value it receive I can't understand.

Thank you.

1 ACCEPTED SOLUTION

robert_straubinger
Product and Topic Expert
Product and Topic Expert
0 Kudos
509

Hello Alesandr,

(now including the pictures properly, sorry), with the help of my colleague Con we have an answer for you. Do you mind telling us what you need in the larger context?

This field defines the method that was used to perform the estimation – it would be updated with QUANTI14 or DEMAND14 variant.

Possible entries are:

Example 1:

Example 2 with custom method:

Best regards,

Robert

View solution in original post

7 REPLIES 7

NicoleHuth
Product and Topic Expert
Product and Topic Expert
0 Kudos
509

Hello Alesandr,

Could you please explain your question in a little more detail and add a screenshot.

Maybe my colleague robert.straubinger can answer your question afterwards.

Best regards,

Nicole

0 Kudos
509

I mean this

Former Member
0 Kudos
509

I mean this

robert_straubinger
Product and Topic Expert
Product and Topic Expert
0 Kudos
509

Hello Alesandr,

with the help of my colleague Con we have an answer for you. Do you mind telling us what you need in the larger context?

This field defines the method that was used to perform the estimation – it would be updated with QUANTI14 or DEMAND14 variant.

Possible entries are:

cid:image002.png@01D3AFBD.31144C90

Example 1:

cid:image003.png@01D3AFBD.31144C90

Example 2 with custom method:

cid:image005.png@01D3AFBD.801F21C0

Best regards,

Robert

0 Kudos
509
Hello Robert. Unfortunatelly I can't see your images.

Actually I understand that:

1. If I bill without meter reading results using estimating procedure -

EXTPKZ gets some value for example "5"

2. If I bill with meter reading results - EXTPKZ is blank.

So quasting is why EXTPKZ gets value 5 or something else?

robert_straubinger
Product and Topic Expert
Product and Topic Expert
0 Kudos
510

Hello Alesandr,

(now including the pictures properly, sorry), with the help of my colleague Con we have an answer for you. Do you mind telling us what you need in the larger context?

This field defines the method that was used to perform the estimation – it would be updated with QUANTI14 or DEMAND14 variant.

Possible entries are:

Example 1:

Example 2 with custom method:

Best regards,