Hi,
In my current client, there is a requirement that in a single contract, different charges use different factory calendar.
Meaning, for example, one contract will have network charge and energy charge. The on/off peak definition of these 2 charges are different. For example, network charge has on-peak 7am-7pm whereas energy charge has on-peak 6am-6pm.
Would this mean one register needs to be assigned to multiple portions (hence factory calendar) ? Is this even possible?
Any advice is highly appreciated.
rgds,
W
2011 Mar 24 11:56 AM
Hi,
Factory calender will assigned at portion for billing purpose, purpose of factory calender is to know the holidays to make changes in bill date and meter reading date and due date only, not for day to day consumption differences for your requirements factory calender no where matters