2013 Nov 14 10:55 AM
Hi All,
My Client's requirement for holiday on scheduled meter reading date is as follows:
If the Scheduled MRD is on Holiday then it must be shifted to the following working day ie Correct Non Working day of MRU must be set to '1'.
SAP has two options :
1 stands for Use the workday following the non-workday
2 stands for Use the workday prior to the non-workday
I am unable to set this value to 1, it is always showing me "Enter 2 in Corr. Holiday field". Incase i am manually entering the value as 1 it is showing as
Quick response would be of great help.
Thanks,
Madhurima.
2013 Nov 15 12:58 AM
Hi Madhurima,
If you want to use option 1-Use the workday following the non-workday, then in that scenario, you have switch on the dynamic scheduling (TE418-TS_DYN) against the MRU.
Dynamic Scheduling has two options-
1-Dynamic scheduling, without budget billing amounts
2-Dynamic scheduling, with budget billing amounts
Depending on your Business requirement, you have to choose either one.
Hope it helps...
Thanks,
Amlan
2013 Nov 21 5:42 AM
Hi Amlan,
I have done the required setting as you said.
I have made Dynamic scheduling active and in portion I have selected
1-Dynamic scheduling, without budget billing amounts. In MRU SAP has made the 'Non Working day' field as readable. Please let me know if any other setting is required.
Quick response would be of great help.
Thanks,
Madhurima.
2013 Nov 21 6:40 AM
Hi,
Are you getting any error after you have switched on the Dynamic scheduling.
I would recommend you to perform a full cycle of testing before moving the changes to Prod.
Thanks,
Amlan
2013 Nov 21 8:34 AM
Hi Amlan,
The basic problem is after making Dynamic Scheduling as active I am unable to do the following setting in MRU :
Correct Non Working Day - '1' stands for Use the workday following the non-workday.
The field Correct Non Working day is showing uneditable.
Thanks,
Madhurima