2014 Apr 07 2:08 PM
Hello Experts,
Need you help to understand this.
When I install a device at an installation I have to maintain a period consumption which form a basis for estimation when required.
In a scenario, I have a device which is installed at multiple installations(billing related), and I change the period consumption through EL56 for one contract(or installation) which does not have full installation of the device.
Now, when I estimate the MR for the original contract which has full installation of the device, the MR gets estimated on basis of the period consumption I maintained through EL56 for another contract, even though I have not maintained it for the contract for which I am estimating. Could you please let me know if my understanding is correct or not? If this is correct, can I avoid it?
Thanks,
Dhiraj
2014 Apr 18 7:55 AM
Hi Dhiraj,
We maintain the Periodic consumption on Device Level not Contract/Installation level in Transaction EL56. ThWhen we enter estimated read it's for device not Contract/Installation. Contract/Installation uses those MY for Billing Purpose.
When you mainatin Periodic Consumption you maintain for Device so when you Estimted the MR for the another contract (But I say for the device) System used the periodic consumption that you maintained before.
In Transaction EL56 the purpose of field Contract/Installation is to Fetch the device.
Hope I am clear enough
Please let me know if you still have doubt.
Thanks, Mohit
2014 Apr 29 5:03 AM
You may need to provide some of your own logic in Enhancement EDMLELHA.