Hi Experts,
Could you please provide your inputs to design below requirement?
We have two different contracts/installations on the premise with same meter assigned to it. First contract is assigned to tenant and second one is assigned to landlord of the premise. They have same billing cycle as well. They are billed together at the end of every month.
Both contracts include consumption and flat charges.
If the first tenant’s contract gets moved-out in between of the billing period, then charges on the second contract (Landlord) contract should be prorated based on No. of Active days of the Tenant's contract.
Example : Billing Cycle : 1st Jan to 31st Jan
Tenant moves out on 10th Jan then charges (consumption charges and flat charges) on Landlord for periodic billing on 1st Feb should be prorated based
on number of active days (10 days for this example).
Thanks in advance!
2016 Aug 30 8:35 AM
Hi Pooja,
As per my understanding we don't have any direct standard SAP solution for this (I am not 100% sure), but we can do this using below custom solution -
1. while performing tenant contract move-out (using EXIT) do disconnection of landlord installation from the move-out date & reconnection while performing move-in (if disconnected).
2. now in the Billing schema if you activate "Disconnected check box" it will resolve your query.
Regards