Hi,
The TCode EMMA, monitering mass runs, when it is executed, even after the Jobs have run successfully,it shows as zero in the columns, viz. No. succesful jobs, Proc. Jobs. in the ECC 6 Version.
Can someone suggest what could be the reason, and if any Notes is to be applied for the same,kindly suggest which one.
Thanks in advance.
Regards,
Irshad Ali Khan.
2009 Apr 01 4:10 AM
2009 Apr 01 7:18 AM
Hi,
Creation of emma case consits of 2 step
1) Prepare Job
2) Create clarification case.
If you need to create the clarification case in that case you will have to select both the check box in transaction EMMA so that it will prepare the job first and then will create the clarification case.
If it is still not happening by doing this then please revisit the configuration of the same.
Regards
Ravi
2009 Apr 02 7:35 AM
Blumtain, Ravi,
Thanks for your response. As told I did, but still I am not getting for the mass bills i.e EA38, EA26 and EA29 but where as the FI-CA related Tcodes, the list shows all the job items, i.e Number of Success, failure and all, and as Ravi said, we need to see the configuration, can you please tell me as where and what has to be done in the settings.
Thnaks again for your valuable inputs inadvance....
Regards,
Irshad Ali Khan.
2009 Apr 02 11:43 AM
HI Irshad,
Please Look into this link of SAP help and you will get to know all the relevant configuration that
needs to be look for.
http://help.sap.com/saphelp_fica472/helpdata/en/79/a23b40b1607a56e10000000a1550b0/frameset.htm
Let me know if you are not clear after this as well.
Regards
Ravi
2009 Apr 07 10:51 AM
Ravi,
Thanks a lot for your valuable inputs, got it.