Hi Experts,
I have to create MRUs in bulk for a client. In transaction E41H 'transport' option is not available. However, it is there in change tcode- E41G.
I checked with our Basis team and it is not an authorisation issue. We are on SAP ECC 6.0. Any help as to how to enable the transport option while creating the MRUs so that it can be transported to other clients?
Thanks in Advance.
Regards,
Twinkle
2016 Jul 08 2:30 PM
Twinkle:
Maintain TE421-cust to enable automatic transport of schedule master records.
regards,
bill.
2016 Jul 08 2:30 PM
Twinkle:
Maintain TE421-cust to enable automatic transport of schedule master records.
regards,
bill.
2016 Jul 11 6:19 PM
Hi Twinkle,
The following SPRO path controls this setting.
SAP Utilities->Basic Functions->Portioning and Scheduling->Define control parameters for Scheduling
Deactivate transport is the field you need to Check\Uncheck based on your requirement.
Regards,
Monis Shakeel
2016 Jul 12 10:35 AM
HI Monis/William,
Thanks for your replies.
I unchecked the Deact. Automatic Transport checkbox(it was checked earlier). But still, I do not get any TR prompt on saving the MRU at the time of creation.
For now, I am first creating the MRU in E41H tcode and then using E41G tcode to save it in TR. Please let me know if you are able to save directly in TR using E41H tcode on saving.
Thanks.
Twinkle Upadhyay
2016 Jul 14 2:36 PM
That flag is the right one. Did you fully exit and then try? Have you debugged to see if checks the table and if/why it does not use standard logic for transport?
2016 Jul 18 5:52 PM
Yes, I did Exit and tried again, isn't working. Will sit with technical team to check.
Thanks for the reply and the suggestion.