Hello Experts,

We have a requirement of adding Move out charges which should automatically gets Posted in customers account (Fpl9),When the Move out is initiated.
Please share the steps to configure the same

Your help and guidance are really appreciated.

Thanks & Regards

Maaz

4 REPLIES 4

william_eastman
Product and Topic Expert
Product and Topic Expert
0 Kudos
225

Have you looked at the charges schema functionality? It is assigned to the movein or moveout control parameters.

AmlanBanerjee
Active Contributor
0 Kudos
225

Hi Maaz,

There is no standard way to process move-out charges.You can customise the BOR object MOVEOUTDOC to have one method, which would trigger a posting of the charges during move-out. An alternate option would be post it at the generation of the Final Invoice using R402 event.

Hope it helps.

Thanks,

Amlan

0 Kudos
225

Good day Amlan,

Thanks for your reply i will try with BOR object by customizing if i get stuck i will be needing your help to finish it

Thanks

Maaz

Former Member
0 Kudos
225

Hello William,

Hope you are doing good

Yes i already gone through with the schema it is only available for Move-in charges which i configured as per the business requirement but for move out i m unable to find the standard process

if i get proper guidance/help i will really be thankful

Thanks In advance

Maaz