Is there provision in IS-U to incorporate Grid Availability"" values/KPIs?
Daily values coming in do have errors which are corrected at the end of the month by new values. This end of month activity is done because there is an incentive allocated to certain availability of grid.
Regards,
Cleo
2013 Oct 31 9:44 AM
Hi Cleo,
You can configure Grids in SAP ISU. But as your question is not clear enough to understand the requirement. Still you can try out the below said configs.
Go to trnasaction EEDMIDE_GRID01 and create a grid according to the requirement/specifications.
To sync this with ISU system, go to installation (ES30/ES31/ES32) and add it there in Point of Delivery field.
Hope this helps..!! If you require more clarity on what I explained, please post your queries.