2013 Apr 09 10:30 PM
FPCRPO - Looking for a configuration point to determine the length of the processing lock (valid to date) that appears on an item in the clarification list once a user decides to lock the item for further investigation, etc.
Thank you
2013 Apr 10 6:29 PM
These items that you have indicated are for lock reasons. I'm looking for the configuration point where I may modify the LOCK_LIMIT field. This field determines the expiration date of the lock. I was thinking that this was supposed to be a new configuration point with the SP4+ for 6.02. If there is no configuration point then I will have to debug to find the location in code. The field exist in table DFKCRPO - the client wants to change the default value, which seems to be 5 days, to a longer point of time.
2013 Apr 10 3:46 PM
HI Kelly,
Not sure what locks you are trying to refer, but these are some of the configuration paths for locks -
SPRO > Financial Accounting > Contract AR AP > Business Transactions > Payments > Incoming/Outgoing payment creation > Define payment lock reasons
SPRO > Financial Accounting > Contract AR AP > Basic functions > Postings and documents >Basic settings > Define lock reasons for posting locks.
thanks,
Vikram
2013 Apr 10 6:29 PM
These items that you have indicated are for lock reasons. I'm looking for the configuration point where I may modify the LOCK_LIMIT field. This field determines the expiration date of the lock. I was thinking that this was supposed to be a new configuration point with the SP4+ for 6.02. If there is no configuration point then I will have to debug to find the location in code. The field exist in table DFKCRPO - the client wants to change the default value, which seems to be 5 days, to a longer point of time.
2013 Apr 11 2:38 AM
Hi Kelly,
Check the following SPRO node-
IMG->Financial Accounting -->Contract Accounts Receivable and Payable-->Technical Settings-->Prepare Processing of Clarification Worklist
Select the application Obj as CRPO and click on Technical Status.
Then Select the Status 02 (In Process) and click on Change icon.
You will find the validity period maintained as 5 days (by default).
In here you can chnage the validity period as per your requirement.
Hope it helps...
Thanks,
Amlan
2013 Apr 11 3:07 AM