Dear all,

I am creating final bill for move-out on 12.05.09. Previous sheduled billing and posting date is 11.05.09. Meter reading is same previous meter reading, zero consumption. During final billing billing document is not generated, it is giving errror

No billing orders exist for contract

Message no. AJ001

Diagnosis

Automatic billing has been initiated without a billing order.

Procedure

Create a billing order and restart billing.

Move-out meter reading is there in the system, but billing order is not generated and billing is not happend. Please anyonne give solution for this.

renju

Edited by: renju metha on Jul 2, 2009 6:43 PM

1 ACCEPTED SOLUTION

anjo_deboer
Explorer
0 Kudos
442

Hello Renju

Look on the installation on the billing period overview.

Look what the billing periods are and you can see also the meterreading status.

Hope this will help you.

otherwise I need more details

Cheers

Anjo

View solution in original post

4 REPLIES 4

rajesh_popat3
Active Participant
0 Kudos
442

Hi,

Please check if the meter reading entered is causing the order to get Implausible. Execute Tcode EL27 and check if any of the reads is implausible, if so, then release the same.

The move out billing order should get created and the billing should get executed successfully.

Hope this helps!!

Regards,

Rajesh Popat

0 Kudos
442

Hi Rajesh,

Initially meter reading was implausible only. But it is released. Then only we are getting this problem.

can anybody suggest solution for this?

renju

0 Kudos
442

Hi Renju,

Is a move-out billing order present? Check on the Installation, then the "Billing Orders" tab if I remember correctly (I don't have SAP up right now). If there is no "move-out billing order", then you might try going to "change move-out" and taking out the move-out reading, then putting it back in and hitting the ENTER button, then saving. Sometimes this will trigger a move-out billing order to be created if one wasn't when the actual move-out doc was created or if it was deleted in error. This would be a system issue though so you might want to check out any SAP Notes as well.

Regards,

Michael

anjo_deboer
Explorer
0 Kudos
443

Hello Renju

Look on the installation on the billing period overview.

Look what the billing periods are and you can see also the meterreading status.

Hope this will help you.

otherwise I need more details

Cheers

Anjo