Error while creating Payment Scheme

Former Member
0 Kudos
254

Hello,

I am new to SAP ISU. I am getting the following error while creating Payment Scheme via Tcode EA61PS.

''Contract account X_CONACT for contract  does not qualify for payment scheme''

The Contract Account has debt items for the past 6 months(that means the customer has to clear the debt for the past 6 months)

Can anyone please let me know under what circumstances can a contract account get qualified for Payment Scheme?

Thank you.

1 ACCEPTED SOLUTION

AmlanBanerjee
Active Contributor
0 Kudos
190

Hi Swati,

Have you activated the Payment Scheme settings in your system.

Go to the following SPRO config for activating the payment scheme-

SPRO--->SAP Utilities--->Invoicing-->Budget Billing Plan-->Basic Settings--->Define Budget Billing Procedures

In here against the company code, the budget billing procedure that you should set for payment scheme should be 01234.

Once done, go to the contract account change screen (CAA2) and set the BB procedure under the general data tab to 4 for payment scheme.

Hope it helps...

Thanks,

Amlan

View solution in original post

3 REPLIES 3

ricky_shaw
Contributor
0 Kudos
190

Hi,

For the  Contract Account try changing the BB procedure field to 3 (Budget Bill) in CAA2 tcode.

AmlanBanerjee
Active Contributor
0 Kudos
191

Hi Swati,

Have you activated the Payment Scheme settings in your system.

Go to the following SPRO config for activating the payment scheme-

SPRO--->SAP Utilities--->Invoicing-->Budget Billing Plan-->Basic Settings--->Define Budget Billing Procedures

In here against the company code, the budget billing procedure that you should set for payment scheme should be 01234.

Once done, go to the contract account change screen (CAA2) and set the BB procedure under the general data tab to 4 for payment scheme.

Hope it helps...

Thanks,

Amlan

0 Kudos
190

Thank you Ricky and Amlan. I am able to create the Payment Scheme