EG42 - Any method to reverse proration?

Former Member
0 Kudos
487

Hi experts,

Any solution to reverse proration date? As user key in a wrong proration date.

Cheers,

Lawrence

1 ACCEPTED SOLUTION

Former Member
0 Kudos
283

Yup,

Execute the transaction again,and revert all the changes done and save.

The time slice should vanish.

If any meter reading was given as part of the process they would either vanish (talking about Reading reason 11 and 16) or change to 09- Control Reading.

Hope this helps.

Cheers,

Rakesh..

sapisurdg.wordpress.com

View solution in original post

1 REPLY 1

Former Member
0 Kudos
284

Yup,

Execute the transaction again,and revert all the changes done and save.

The time slice should vanish.

If any meter reading was given as part of the process they would either vanish (talking about Reading reason 11 and 16) or change to 09- Control Reading.

Hope this helps.

Cheers,

Rakesh..

sapisurdg.wordpress.com