I want to do fortnightly billing and want to create scheduled meter reading orders on 15th and on last day of every month.

Putting time interval 15 days in portion is not useful here. Please suggest.

Regards,

Jayant

1 ACCEPTED SOLUTION

kevin_dewilde
Active Participant
0 Kudos
161

You can add a 02 in the definition of your meter reading unit (click the + button at the top of the screen). However, I'm not sure if those are launched automatically this way.

If not, there's always the possibility of a Z-program to schedule 02 creation...

View solution in original post

3 REPLIES 3

kevin_dewilde
Active Participant
0 Kudos
161

Jayant,

I don't think you'll be able to do this with only periodic meter readings.

A work around I could suggest is making a <i>monthly</i> portion on the last day of the month, and adding a 02 MR in the meter reading unit on the 15th of the month.

Of course, I don't know if this suits your business requirements...

Regards,

Kevin

0 Kudos
161

Thanks Kevin.

Can I create 02 orders automatically on 15th of every month?

Can I use 'control group in register' for that? Do u have any idea?

Regards,

Jayant

kevin_dewilde
Active Participant
0 Kudos
162

You can add a 02 in the definition of your meter reading unit (click the + button at the top of the screen). However, I'm not sure if those are launched automatically this way.