2011 Aug 19 5:35 AM
Hi experts:
We have current implemented for the scenario in mention the WF ISU_ASSESS, but now we are evaluating the standar functionality DPC (Dynamic Period Control) for a possible change.
I need know if DCP supports the following points:
- Demand calculations
- Overflow (Last estimated meter reading result is greater that current real meter reading result)
- Move out/ Move in
- Meter reading result in Removal/installation (replaced device)
- Update consumption values in the instalation facts
- Update consumption history
Regarding INVOICING, it is necessary to adjust some event (Ex. R-403)?
Any comments, experiences or suggestions will be very welcome.
Thanks a lot.
David
2011 Aug 22 7:23 PM
Hi David,
Most of the points you mentioned will be taken care by DPC but to have more information there is a cookbook on SAP service place.
https://websmp103.sap-ag.de/utilities
SAP for utilities - product information > ISU-CCS > Billing & Invoicing > cookbook & guideliens > Dynamic Period Control.
Thanks,
VR
2011 Aug 22 7:23 PM
Hi David,
Most of the points you mentioned will be taken care by DPC but to have more information there is a cookbook on SAP service place.
https://websmp103.sap-ag.de/utilities
SAP for utilities - product information > ISU-CCS > Billing & Invoicing > cookbook & guideliens > Dynamic Period Control.
Thanks,
VR
2011 Aug 23 2:44 AM