2011 Nov 16 9:16 PM
Hello Colleagues,
I am trying to determine how the Processing deadline works for Collections Work Items in IS-U.
If I assign a Work Item Category a Processing deadline of 7 days, (Mandatory = Blank) and I trigger a Work Item today, I can see that the Run Date on the header table DFKKWL is set to 7 days past the creation date of the Worklist.
However, when I do run dunning with Issue date 7 days later, the Work Item is not closed (Still Open). This is not an enforcement work item.
If you have successfully worked with Processing Deadlines before, I'd really appreciate it if you could share your experiences.
Thanks a lot.
Regards,
Ivor Martin
2011 Nov 16 9:31 PM
Ivor:
Processing deadline has no functionality behind it - it is informational. it should be used by the manage in FPWLM to close the workitems which have reached their deadline.
regards,
bill.
2011 Nov 16 10:00 PM
2012 Jun 12 2:19 PM
Hi William,
in my project we want to use processing deadlines to automatically close work items when run date is past for work items (mandatory= blank and enforcement= blank) which are still open (statuts New or In process). This should be done before dunning is launched each day.
I understood that the processing deadline is informational and has no functionality in dunning.
But I was hoping that a standard way would exist do it? (in function module FKK_0350_WLI_CREATE_AND_CLOSE, or other standard program to launch)
I didn't find anything about that and any help would be appreciated.
Thanks a lot.
Regards,
Emilie