Hi experts,

I'd like to manually change the "Gas allocation date" of a Meter reading document : EABL-THGDATUM

I do not want to use  EXIT_SAPLEL01_009 (IS-U: Change Gas Date in Meter Reading Processing).

Could you tell me if it is possible with SAP standard transactions?

Thank you for your help.

Regards,

Philippe

2 REPLIES 2
Read only

philippe_tsalos
Participant
0 Likes
414

Still unanswered

Read only

Former Member
0 Likes
414

Dear Philippe,

You can check BAdI ISU_QD_GAS_DATE_CHANGE.