I want to create new factory calendar, and assign it to portion with older orders.
Someone think that there is a problem to do this?
thanks....
2015 Oct 07 8:23 PM
Change the portion (E41C), activate the portion in meter reading units where used (E41G) you will see the factory calendar assignment flip over to the new one. Regenerate the schedule records (E43A / E*DY). I suggest practicing in a playpen so you can get a feel for the activity. Dynamic schedules need special care in my opinion.
good luck.
2015 Oct 07 8:23 PM
Change the portion (E41C), activate the portion in meter reading units where used (E41G) you will see the factory calendar assignment flip over to the new one. Regenerate the schedule records (E43A / E*DY). I suggest practicing in a playpen so you can get a feel for the activity. Dynamic schedules need special care in my opinion.
good luck.
2015 Oct 08 6:56 AM
My 2 cents
Dynamic Schedules need the Factory Calendar to be mentioned when created. So they are dependent on the FC for each of their transactions. Now if we want to change the FC in Dynamic Scheduling, we need to check
1. No Billing Orders Exist.As Dynamic Schedules transaction work on Month basis so all MRO for the month should be read and billed.(Generally Business go for such changes at End of year to save on complexities.)
2. Pendng Schedules should be deleted.
3. FC should now be changed in portion.
4. Now with the new FC and the starting month the dynamic schedules can be generated.
There are issues in dynamic Schedules cause of which sometimes it doesn't allow one to delete generated schedules, so keep a tab on the standard tables for schedule records of Portion and MRU for consistency. And As David mentioned practice it in sandbox first .
Cheers,
Rakesh..