2009 May 06 6:18 PM
Hello,
What we are trying to do is to realign a number of business partners to a particular set of contract accounts. We essentially converted from a non SAP solution to CCS and now see a need for reassignment of contract accounts to different business partners. One way of doing it is to follow move out and move in process, but that has downstream process complications. What other options are you aware of that we could pursue?
Thank you,
Mike
2009 May 07 10:44 AM
Hi Mike,
For changing the relationships of business partner and contract account, you have to do the Move-out and Move-in. If this huge laborious task then you can record the process in SHDB and create a BDC or a LSMW for this task.
With Regards,
Sunil
2009 May 11 12:27 AM
hello Mike,
Perhaps could use a change contract with invoicing or w/o change contract.
for more information: http://help.sap.com/erp2005_ehp_04/helpdata/EN/00/eec6b8068311d5b4290050045628ea/content.htm
regards
Anderson Morita