2013 Jun 26 1:29 AM
I have two questions for you
Firstly,
I don't want to use budget in specific commitment item
How can I except for it?
this commitment item's financial trans is 50, and commitment item cat is 2
and I can see it from FMIFIIT table but I don't
I usually use this asset retirement, tranfer or acquisition
before I upgrade SAP version from 4.7 to ECC 6.0, It didn't happen
Secondly,
After PO, I canceled it but still grab some budget
and I can't use that budget anymore
How can I back to my budget before PO?
Thanks in advance
2013 Jun 26 8:30 AM
Hi,
a) There are different ways. The most simple one is to define commitment item as 'statistical'. Keep in mind, that financial transaction and categories have other meanings and bare other functions, along with budget check.
b) If your PO is cancelled and you see that the commitment is reduced (could be checked directly in FMIOI table), then your budget will be returned to the year of consumption
Regards,
Eli
2013 Jun 26 9:35 AM
Hi Eli
a) How can I define commitment item as 'statistical'?
Do I have to use override update profile?
b) then, I can't use that budget anymore before return it can I ?
If I use that budget right away then do I have to add additional budget?
Thank you for your answer
Best wishes,
2013 Jun 26 10:37 AM
Hi,
a) In master data of commitment item
b) If the budget is consumed, certainly, you cannot use. Once it's released with commitment reduction (after cancellation of PO), you can.
Regards,
Eli