SAP for Public Sector Discussions
Foster conversations about citizen engagement, resource optimization, and service delivery improvements in the public sector using SAP.
cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Provision entries to be excluded from budge contorl

Former Member
0 Kudos
399

Hi,

We are on ECC6, EHp4, and already live 4 years back with SAP. Now, we want to exclude the provison entries from budget control. I understand,I can do the same by creating the new docment type. But in derivation rule the document type I see are the FM document type which are created for budget uplaod, am I correct?

How do I do this? Can anyone advise please.

Reards

Shaileh 

1 ACCEPTED SOLUTION
Read only

iklovski
Active Contributor
0 Kudos
339

Hi,

There is no link between budgetary FM document type and FI document type. If you want, indeed, to exclude certain FI document type from budget control, create a derivation rule in FMDERIVE, deriving dummy/statistical commitment item for the relevant type.

Regards,

Eli

View solution in original post

4 REPLIES 4
Read only

iklovski
Active Contributor
0 Kudos
340

Hi,

There is no link between budgetary FM document type and FI document type. If you want, indeed, to exclude certain FI document type from budget control, create a derivation rule in FMDERIVE, deriving dummy/statistical commitment item for the relevant type.

Regards,

Eli

Read only

Former Member
0 Kudos
339

Thanks Eli,

Does that mean the Doc Type I see in the derivation rule is normal doc type?

Will check once again and confirm ...

Thanks...

Shailesh....

Read only

iklovski
Active Contributor
0 Kudos
339

Yes, document type in source fields which you see in FMDERIVE, is FI document type (BLART).

Read only

Former Member
0 Kudos
339

Thanks Eli,

Will try it.

Thanks

Shailesh