2016 Feb 11 12:26 PM
Hello,
We have a requirement that the PO is created for 3 year period, but the budget to be consumed in different years.
For Example:-
PO created in 2016 for 30000 pertaining to 3 years 2016,2017 and 2018.
Commitment should appear as 10000, when i check in 2016 report, 10000 in 2017 report and 10000 in 2018 report.
How can this be achieved.
Business cannot split the PO in to 3 line items or it cannot create 3 PO's because of agreement conditions.
Regards,
Rajesh
2016 Feb 11 2:06 PM
Hi,
Without splitting PO in 3 lines and establishing FM posting date as 'delivery date' (by selecting relevant FM update profile or overwriting existing one), you won't be able to achieve this.
Regards,
Eli
2016 Feb 11 2:06 PM
Hi,
Without splitting PO in 3 lines and establishing FM posting date as 'delivery date' (by selecting relevant FM update profile or overwriting existing one), you won't be able to achieve this.