2014 Mar 27 6:30 AM
Hi Experts,
I am facing payment budget check issue during the reversal of GRN. I was wondering why the system is checking the budget at the time of reversing the GRN, is this standard behaviour of the SAP?
PR Created 1000 USD
PO raised 1000 USD
GRN Done 1000 USD
During the reversal of GRN, the availability amount for the Fund center and Commitment item was only 500 USD, so the system is thowing the error message as budget exceeded by USD 500 when doing the GRN reversal
Please help to clarify on the above issue how to stop budget check during the reversal of GRN. We are using updating control as MM Goods Receipt in OFUP
Thanks & Regards
**********************
Kumar
2014 Mar 27 11:03 AM
Hi Experts,
I am facing payment budget check issue during the reversal of GRN. I was wondering why the system is checking the budget at the time of reversing the GRN, is this standard behaviour of the SAP?
PR Created 1000 USD
PO raised 1000 USD
GRN Done 1000 USD
During the reversal of GRN, the availability amount for the Fund center and Commitment item was only 500 USD, so the system is thowing the error message as budget exceeded by USD 500 when doing the GRN reversal
Please help to clarify on the above issue how to stop budget check during the reversal of GRN. We are using updating control as MM Goods Receipt in OFUP
Thanks & Regards
**********************
Kumar