2010 Aug 26 12:09 PM
Hello All
We required BCS to have departmetn wise budgetary control.
The maintenance department has its own budget that needs to be check at the time of maintenance departmetn activities like procrument , labour exp etc.
There are some automatic generated Maintenance order where we cannot manually put budget is there any way to put the budget on maintenence order.
Thanks
ALOK GUPTA
2010 Aug 26 12:26 PM
Hi,
The budget is always put on FM objects, e.g. fund centre, commitment item, fund, etc. You can develop derivation strategy via FMDERIVE to exract the releavnt budget objects based on the transaction parameters. For maintenance orders, don't forget to activate the integration between PM and FM.
Regards,
Eli
2010 Aug 26 12:26 PM
Hi,
The budget is always put on FM objects, e.g. fund centre, commitment item, fund, etc. You can develop derivation strategy via FMDERIVE to exract the releavnt budget objects based on the transaction parameters. For maintenance orders, don't forget to activate the integration between PM and FM.
Regards,
Eli
2010 Aug 30 3:30 AM
2010 Aug 30 9:08 AM
IMG - Public Sector Management - Funds Management Government - Actual and Commitment Update/Integration - Integration - Maintain Field Status for Assigning FM Account Assignments.