2011 Jan 31 1:52 PM
Dear Experts
We are implementing Funds Management - BCS.
We request you to clarify that how to exclude some of g/l accounts from budget checking. (Here we need to give budget for all commitment items/fund center for variance calculation, but system should not stop when actual values exceeds budget values for SOME of g/l accounts only in BCS).
Kindly post your valuable replies to help us.
Thanks and Regards
PVSRG
Moderator: Please, search SDN
2011 Jan 31 2:08 PM
Hi.
You can do it using additional account assignments(eg Funded program).In fmderive write logic like If Gl account 1, then FP=A.
In Filter for Budget profile If FC=A, then profile=None.
Or test EXIT_SAPLFMFA_001 for statistical update. there a structure ACCIT, where HKONT exists.