2018 Oct 31 9:29 AM
Hi All,
Funds Reservation is the starting point in our transactions, with reference to FR a PR will be created and with reference to PR a PO will be created. (FR-->PR-->PO-->GR-->IR-->Payment).
There are some PO's and made payments against these PO's, now we found that the Account assignment is wrongly assigned and now we wanted to change these account assignments.
Our derivation strategy is in combination of Fund and WBS element mentioned in the FR, which derives the Fund center and Funded Program. same account assignment elements are copied through FR, PR, PO, IR and Payments.
Requesting all to provide an approach to do the correction of Fund Center, Funded Program, WBS element in these documents.
Thanks
Prashanth Ragi
2018 Nov 05 9:09 AM
Hi,
By account assignment, do you mean FM assignment or CO (G/L, cost centre, WBS, etc.) assignment? If the first is correct, then you can use reassingment programs of FM. If the second is correct, there is no other way, but to decommit the documents and repost them.
Regards,
Eli
2018 Oct 31 11:58 AM
2018 Oct 31 1:12 PM
Thank you for your suggestion. Reclass option is not our first choice as client wants the various reports to reflect the corrected assignments.
Also the PO's with incorrect assignments are not fully consumed yet. so we are looking for a solution to change the account assignments in the source document.
Thanks
Prashanth Ragi
2018 Nov 05 9:09 AM
Hi,
By account assignment, do you mean FM assignment or CO (G/L, cost centre, WBS, etc.) assignment? If the first is correct, then you can use reassingment programs of FM. If the second is correct, there is no other way, but to decommit the documents and repost them.
Regards,
Eli