Budget compromise by releasing requisition purchase order (ME54N)

former_member211458
Participant
0 Kudos

hello Experts, please a consultant

It is possible to configure in FM for the budget compromise at the time of the release of the requisition (ME54N) and not when creating the purchase requisition (ME51N)?

greetings and thanks for the suggestions

Augusto

3 REPLIES 3

iklovski
Active Contributor
0 Kudos

Hi,

Do you mean consume the budget at the time of release and not on the creation? It won't be possible, due to prudence policy in PSM-FM. Imagine, creating a lot of PRs, which won't have effect at the budget and the lack or resources will be discovered only at their release.

Of course, by modifying standard code, in theory, you can force this kind of logic, but I won't recommend it both from technical and functional reasons.

Regards,


Eli

0 Kudos

Hello Eli:

I once had the same requirement from client and i satisfied them by giving the same argument as you gave .

Thanks

iklovski
Active Contributor
0 Kudos

Hope Augusto's client is as easy as was yours