2014 Oct 18 10:45 AM
Dear Users,
As subjected, system is checking for budget while performing GRN even after reconstruction of PR and PO's. Please suggest with any possible solutions for this error.
Thanks & Regards,
Manoj
2014 Oct 21 7:49 AM
Hi,
What is the connection between budget checking and PO reconstruction? Can you please specify your problem?
Regards,
Eli
2014 Oct 22 4:59 AM
Dear Eli,
Thanks for reply, we have recently implemented funds management and we have some Open POs for which GRN is pending. So we have reconstructed all open POs to bring them into budget so that system should check for budget only at PO level but still system is asking for budget while performing GRN. Please help out with possible solution.
Thanks,
Manoj
2014 Oct 22 7:50 AM
2014 Oct 22 8:15 AM
Yes we have commitment and budget, but in budget report it is showing negative value. But the budget restriction is at PR level why it is checking for budget at GRN level.
Thanks,
Manoj
2014 Oct 22 8:20 AM
It is not what I asked: do you have commitment budget and payment budget categories? In other words which FM update profile are you using?
2014 Oct 22 11:36 AM
2014 Oct 22 11:47 AM
These are FM objects, not categories. What is the value in OF37 transaction?
2014 Oct 22 11:53 AM
2014 Oct 22 12:20 PM
I'd say I'd suggest you to check this with the person who configured FM for you, as I cannot get details from your feedback in order to give you an answer